31 August
(looking SE):
The exterior walls of the lower level are framed.
Some structural steel needs to be added,
then the floor joists can be installed.
The 1,000 gallon water tank has moved since the picture at top was
taken;
it needs to be put into the crawl space before the joists can go up.
We are short 2 framers for now,
but hope to have a full crew within a week.