| We were travelling during late September and early October. In that time, the three level floor deck of the upper floor was finished, concrete was poured to replace the damaged portion of the Garage roof, timbers were erected to connect the Garage to the west end structure, and framing began on the upper level. Since our return, ... |
|
|