02 Jul 2007 – ESE The first plank of flooring is laid. |
03 Jul 2007 – NNW Paul and Ken discuss details of timber trim along the top wall of the Kitchen. A stainless steel shroud will hide the duct for the range hood. |
03 Jul 2007 – W Wood flooring extends from the Kitchen, through the Dining Room, into the Great Room. |
|---|---|---|
|
07/07/07 – S The Entry is ready for concrete. This gives some idea of the finished grade. |
09 Jul 2007 – SE Positioning boulders that will be in the South Patio slab. |
09 Jul 2007 – WNW [600KB movie] Paul does some finish carpentry with a chain saw. |
|
09 Jul 2007 – NNE Stainless steel shroud and the timber trim are installed in the Kitchen. |
09 Jul 2007 – W The gun racks Gary made are installed in the Stairwell. The guns will wait until we move in. |
09 July 2007 – S Adam, Lars and Paul start to test fit the beam between the Entry and Great Room. |
|
09 Jul 2007 – S Paul and Adam adjust timber trim between the Entry and Great Room. Lars operates the lift. |
09 Jul 2007 – NNW Glass is installed in the Master Bath Shower. |
09 Jul 2007 – NW South Patio is ready for concrete. |
|
09 Jul 2007 – W Master Bedroom Patio is ready for concrete. |
14 Jul 2007 – NNE The Kitchen floor is ready for cabinets. |
14 Jul 2007 – SW Master Bedroom Patio is finished. |
|
14 Jul 2007 – WNW The South Patio awaits the mason to finish the pillars. Compare with October, 2005. |
14 Jul 2007 – ENE The Lower Patio is finished. |
16 July 2007 – S Timber trim between Entry and Great Room. Still need to wrap the steel pillars. |
|
17 July 2007 – ESE Pauline admires cabinet installation in progress. |
17 July 2007 – W Panorama of the Great Room taken through the Dining Room. Curvature of the beam at top is due to the fish-eye effect of the lens. Steel pillars at right will be wrapped to look like timbers. |
19 July 2007 – W Panorama of the Great Room with test fit of timber posts in place. |
|
24 July 2007 – SW Entry slab is setting up while other workers install gutters. |
24 July 2007 – ENE Looking from the Great Room to Lars in the Library; the timber trim is almost ready for the painters. |
24 July 2007 – SW This is how the slab is textured [900KB movie]. |
|
24 July 2007 – NE Making templates for the Kitchen cabinets for the granite counter tops. |
25 July 2007 – ENE Pauline admires framing for the half-height wall that separates the Dining Room from the Promenade. |
25 July 2007 – SW Cabinet hardware matches doors and balusters. |
|
25 July 2007 – N Door hardware. Looks like another touch-up job for the painters. |
27 July 2007 – NNW Master Bath shower with tile floor pan installed. |
27 July 2007 – NE Almost ready for the Jacuzzi! |
|
27 July 2007 – ESE Wine is in the Wine Cellar; racks come later. |
31 July 2007 – SE The pillars start to get their cloaks of stone. |
31 July 2007 – NW Looking across the Dining Room to the half-height wall, now with wall board. |